Sketch of structure with sluices up
This structure, which
is to be opened by the Lord Provost on Saturday, is a somewhat unique type of
cross-river bridge, the only similar one in Britain
being across the River Thames at Richmond .
The Lord Provost of Glasgow
at that time was Samuel Chisholm.
Somewhere about 20
years ago, after much discussion, it was decided by the then Town
Council that the old weir, which consisted of a rough bank of stones and boulders of various
sizes submerged at high water, and which extended across the river about 100
yards east of
Albert Bridge, having a lock for the passage of boats at it’s north-end,
should be removed, in the
expectation that various good results would follow,
including less dredging in the harbour, and
unimpeding navigation as far as Carmyle.
Far from improving
maters, however, the immediate effect of this step was an enormous
amount of scour in the river bed, causing the river banks for long stretches to cave in,
and also
seriously injuring the foundations of several of the river bridges,
the old Rutherglen Bridge being
the first to show dangerous symptoms, which
ultimately led to its being taken down and replaced
by the present handsome
structure, whilst the amount of dredging in the harbour was probably
increased by the deposit of the scoured-out material.
After considering the
question for some time, and studying the result of the new weir just them
finished at Richmond on the ‘stoney’ principle, the Corporation decided to erect
a similar structure
on the site of the old weir, as a result, Parliamentary
powers were obtained in 1892.
The work of
construction was not begun until a year or so later, but following very severe
flooding, the coffer-dam, which had been constructed by the first firm of
contractors who
undertook the work, was undermined and a great amount of damage
done, the final result
being that the Corporation took over the works from
them. Sir Benjamin Baker, the well known
engineer, was called in by the Corporation, and, after a careful examination, be recommended
the carrying out
of the works by the sinking of a series of caissons extending from bank to bank
by the pneumatic process, which he had employed so successfully at the Forth
Rail Bridge.
Fresh designs were prepared under the supervision
of the City
Engineer, and a new contract was let, the successful offerers being Messrs
Morrison & Mason Limited, and work was again resumed in the latter end of 1896.
The firm of Morrison & Mason specialised in building waterworks,
docks, railway
construction, tenements, villas and public and commercial buildings.
Amongst some of their work in Glasgow
between 1875 – 1908:
The General Post Office, George
Square
Her Majesty’s Theatre (Citizen’s Theatre), Gorbals Street
Colliseum Theatre
And possibly most famously – Glasgow
City Chambers (1882 –
1890)
Progress Of The Work
Since that date the
work has been quietly but steadily carried on under many difficulties,
particularly during the winter seasons, which since the work was resumed have
been of a
very wet description, the river being in flood to a greater or less
degree for weeks at a time.
The delay has arisen chiefly from the great
difficulty which was experienced in sinking the caissons
through the solid
masonry foundations of the old lock already mentioned and through the boulders
etc., forming the old weir, which had made their way many feet down into the
sandy bed of the
river, and caused a great deal of trouble when getting below
the cutting edges of the caissons.
The series of sill caissons, which were sunk
right across the river, had to be finished one by one,
the work at one being completed and the water-way restored before another was started,
this being
absolutely necessary owing to the amount of scouring action which immediately
took
place when the water-way was restricted by their presence. As only four
men could be employed
in one of these caissons at a time, the rate of speed was
necessarily slow, and the daily amount
of sinking accomplished, even in the easiest material, very small. They are sunk to a depth of 45
to 50 feet below
high water, so that their foundation is well below the limit of any scour which
could possibly occur in the future.
Operations Below Low
Water Mark
Very great amount of
accurate work had to be carried out below low water mar by the aid of
pumps or
by divers, and as even the most powerful pumps were unable to control the water
except for a short period at low water of each day during the period of spring
tides, the
operations were necessarily prolonged. In fact, many of the portions
of the work carried out
have no precedent in engineering operations, in that no
benefit was obtainable from prior
experience gained in similar work, and many
expedients were tried from time to time by the
contractors to solve the various
problems, and great credit is due to them for the manner in which
they have
finally overcome all difficulties. It is also a matter for congratulation that,
in spite of the
somewhat risky nature of the pneumatic process of forming
foundations, especially in tidal
rivers, no fatal accident has occurred since
the commencement.
The structure is now quite complete and the sluices in
working order, the only thing remaining
to be done being the drawing of old
piling and the placing of a new skin of heavy slag all over the
river bed, so
as to prevent any scouring action in the future.
Division Of The Weir
The type of weir
adopted, as already mentioned, is that patented by the late F.G.M. Stoney
and consists of three large sluice gates 80 feet long by 12 feet deep, each closing
up one of
the three 80 feet spans into which the weir is divided. These gates
weigh about 45 tons, but
20 tons of counter-balance weight is provided at
either end, so that only five ton net lift remains.
The lower edges of these
gates, when down for the purpose of damming up the water on the
upstream side, is in very close proximity to a massive granite sill by the caissons formerly
mentioned, but is not closed right down on it, a sufficient space being left so
that just enough
water gets away underneath to ensure that the ponded up water
on the upstream side shall
remain at a constantly uniform level. When there is
a large amount of water in the river these
openings will be increased, and when
a small amount, diminished. At high water, or shortly
after it, the gates are
shut down and while the tide recedes on the down-stream side as it does
ordinarily on the up-stream side, the water remains at the level it held when
the gates were shut
down, thus ponding up the water, and forming practically a
long lake extending beyond
Dalmarnock Bridge, and as a consequence preventing
that unsightly exhibition of
mud and garbage, and in summer the objectionable
smell from decaying matter which
are observed at the present.
Navigation
Arrangements
On the incoming tide
rising and reaching the level of the ponded-up water on the up-stream
side, the
water pressure on the gates is naturally equalised, and the gates are then
lifted and
navigation allowed to go on unimpeded as through an ordinary bridge.
As the gates rise they are
tilted over into a horizontal position, until the
face of the sluice gate is at the same level as the
crown of the arch, and the
appearance of an ordinary bridge is obtained. Each gate is raised and
lowered
by a small hydraulic engine situated in the centre of each span, and the
process of lowering
or lifting a gate takes about three minutes. As a final
result of the undertaking, the dilapidation of
the river banks will be stopped
and it is confidently expected that when they are restored, the
stretch of
river lying to the east of the weir will once more become a boating centre, and
with a
purified river, which is not very far distant, will once more prove an
attraction to the citizens, and,
instead of being an eyesore, become the scene
of much healthy and enjoyable recreation, not
very different from what obtains
on the Thames at present.
Engineers and
Contractors
It should be
mentioned that the engineer in chief for the whole works has been Mr. A. B.
McDonald, M.Inst.C.E., the City Engineer, with Mr. John Cowan, Assoc.
M.Inst.C.E., as
resident engineer, while Messrs Ransomes & Rapier (Limited)
of Ipswich, have erected all the
steel work of the superstructure, as well as
the ‘Stoney’ sluices, the foundations, masonry, and
general work being executed
by Messrs. Morrison & Mason (Limited), Polmadie.
Completed Bridge, 1901
The bridge remained
until 1941 when flooding to the surrounding area
occurred - scour
undermining the abutment foundations. At this time, both the structure and
the tenements
on Adelphi Street
on the south bank were demolished.
The present bridge
was completed in 1949 and carries pipes across the river.
Bird's Eye View showing Glasgow Green on the north bank.
www.memento-mori.co.uk
This is a great article and very helpful in giving some of the construction details of the original weir. Thanks a lot for making this available.
ReplyDeleteI've been looking at the weir recently and the 1894 Act that allowed construction. All very interesting.